Hi Guys,
I performed the following steps on P6:
1. Export P6 schedule from Project A into excel.
2. Import activities and activity relationship from Project A excel spreadsheet into Project B.
Then, I ran a P6 schedule and was going through the log. I noticed that the log said "Milestone Activities with invalid relationships". These were the milestones that I had imported from another project.
Do you know why this error message showed up? The activity codes and relationships seems to look exactly like the old project.
Please help!!
Thanks.
I performed the following steps on P6:
1. Export P6 schedule from Project A into excel.
2. Import activities and activity relationship from Project A excel spreadsheet into Project B.
Then, I ran a P6 schedule and was going through the log. I noticed that the log said "Milestone Activities with invalid relationships". These were the milestones that I had imported from another project.
Do you know why this error message showed up? The activity codes and relationships seems to look exactly like the old project.
Please help!!
Thanks.