Invalid Relationships & Not ideal critical path!

3 replies [Last post]
Jojie Pepito
User offline. Last seen 6 years 12 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 15
Good day !

I need your help...

facts,

1. I have 800 activities on my scheduled project that mainly consist of 24 buildings and roadworks.
2. When i scheduled the project, there are 46 milestone activities which have an invalid relationships.
3. All this activities were completion activities which are linked to project completion.
5. Please advice me on how to resolve this problem.

and my expected critical path was not the one appeared on the scheduled project. Advice please!!!!!!!11

Replies

Maghsoud Joudi
User offline. Last seen 13 years 40 weeks ago. Offline
Joined: 15 Nov 2004
Posts: 9
Change your bar view to show float as well. You have some activities with no successor or long float which changes the critical path.
Jojie Pepito
User offline. Last seen 6 years 12 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 15
Thanks for the reply!

All the invalid relationships has an Finish milestone actvity type because it is all completion works.

I need to determine the logical and real critical path but the result is very far from reality.

Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
try using finish milestones and FF links (for invalid relationships)

for expected critical path - try to use FS links (only!)