Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P3e advise for Beginner

1 reply [Last post]
Paula Cohen
User offline. Last seen 16 years 12 weeks ago. Offline
Joined: 26 Sep 2005
Posts: 4
Groups: None
A one minute lag seems to have been introduced into my schedule. I plan in days, with either a one-working day weekend or 5-working day mid-week calendar being assigned. The shift patterns are 08:00 – 17:00 for both. However activities with a one-day duration started extending over two dates. When I looked at the start and finish minutes, instead of starting at 08:00 the activity was starting at 08:01 and finishing the following day at 08:01. When this additional minute is manually removed the finish time reverts back to 17:00. My lag between activities is always in full days. The resources allocated to the activities also have the same shift times.

As I have only been doing P3 planning for a few months, this has stumped me.

Please help.....

Replies

Bill McMichael
User offline. Last seen 12 years 38 weeks ago. Offline
Joined: 12 Dec 2004
Posts: 73
Groups: None
Paula,

Do you have resources assigned to the task ? If it is a driving resource, there may be a rounding issue if there is a very small units per time where it causing your remaining duration to be recalculated to not be a whole day.

You may want to check if your duration type for the activity is "Fixed duration and Units" if you do not want your duration to be recalculated.

Regards,
Bill