P6 Beginner Question - Can you delete same predecessor from multiple activities

1 reply [Last post]
sam dsoza
User offline. Last seen 6 years 24 weeks ago. Offline
Joined: 20 Jun 2006
Posts: 55
Groups: None

Hello All,

So I am not new to P6 but have forgotten most of the skils for not having to use it.

My question as the subject line mentinos is if you could delete predecessor form multiple activities. Please advice.

 

Thanks

SD

Replies

Zoltan Palffy
User offline. Last seen 23 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

within P6 you can only delete multiple predecessors from and activity but you can not delete the same predecessors from multiple activities.

You can do this with sdk and the associated spreadsheet.

EVERYTHING is based on the activity id not the predecessor id