P6 Beginner Question - Can i change the start day of the project ?

2 replies [Last post]
shawkat matar
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 13 Feb 2016
Posts: 2
Groups: None

Can i change the start day of the project ?

Replies

Zoltan Palffy
User offline. Last seen 27 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you wil also want to change your data date to equal your start date 

Irfan Khan
User offline. Last seen 16 weeks 9 hours ago. Offline
Joined: 19 Jul 2009
Posts: 138

Dear Shawkat,

 

You can chnage/Modify your start date @ anytime by following these steps :

 

1 - open your project & go to Project Window

2 - Click on Date Tab

3 - You can see there an option "Project Planned Start" just change it to your desired date you want.

 

hope this will help

 