Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Replace activities - Percent physical progress changes?

6 replies [Last post]
Carlos Pereira
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 22 Jul 2010
Posts: 16
Groups: None

Hi guys, I would like to share something that is grinding my gear…

 

I am working in a project of 4years duration with a big manufacturing scope (there are as well Eng and Procurement).

It includes a high number of identical components planned to be manufactured in a similar period of project. These components are very critical to the project and they have almost the same contractual date. The only difference between them is the shipment. Each one is planned to be delivered in a specific site of the client, and we report to the client the overall progress as well as the individual progress.

The problem I am facing is regarding to change management.

 

When a component "A" delay or takes a nonconformity for instance, often the mitigation plan requested by the Manufacturing guys to avoid losing the contractual date is to submit a change request, asking for replace the defective component to a similar one "B", healthy and on time.

 

The perspective of mitigation is totally plausible and acceptable since we assume here that all studies of mitigation has been done so far, but look the changing scenario below:

- component A: defective; 85% physical percent completed; contractual date May/2015

- component B: healthy; 70% physical percent completed; contractual date Jun/2015

 

On the planning perspective, replacing "B" on "A" means decrease 15% (85% - 70%) of the progress and assume the new planned finish date. Remember that in this case we have 3 reports to the client: the overall contract, the EPC "A", and EPC "B". The % of the overall will not change, but individually will.

 

In your opinion, how is the better way to handle this situation?

Thanks a lot,

Carlos

Replies

Carlos Pereira
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 22 Jul 2010
Posts: 16
Groups: None

any thoughts?

Carlos Pereira
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 22 Jul 2010
Posts: 16
Groups: None

any thoughts?

Carlos Pereira
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 22 Jul 2010
Posts: 16
Groups: None

Hi Mike, 

The time to rectify does not take to long, but actually the problem is the slot plan on the machining shop. It is necessary to wait for a window in the machining to "A" get in again, because the machining cycle time is long.Sometimes another issue happens when due to the internal capacity, the "A" is manufactured outsource. This involves more time for inspection and sometimes, due to the complexity, the component come back to rectify in-house, affecting the slot plans... 

Carlos Pereira
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 22 Jul 2010
Posts: 16
Groups: None

Hi Mike, 

The time to rectify does not take to long, but actually the problem is the slot plan on the machining shop. It is necessary to wait for a window in the machining to "A" get in again, because the machining cycle time is long.Sometimes another issue happens when due to the internal capacity, the "A" is manufactured outsource. This involves more time for inspection and sometimes, due to the complexity, the component come back to rectify in-house, affecting the slot plans... 

Carlos Pereira
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 22 Jul 2010
Posts: 16
Groups: None
Hi Mike, The time to rectify does not take to long, but actually the problem is the slot plan on the machining shop. It is necessary to wait for a window in the machining to "A" get in again, because the machining cycle time is long.Sometimes another issue happens when due to the internal capacity, the "A" is manufactured outsource. This involves more time for inspection and sometimes, due to the complexity, the component come back to rectify in-house, affecting the slot plans... 
Mike Testro
User offline. Last seen 35 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Carlos

How long does it take to rectify the defect on A.

Best regards

Mike Testro