Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Why is that some people believe you cannot use Physical percent complete if the schedule is not resource-loaded?

1 reply [Last post]
Matt Ir
User offline. Last seen 7 years 6 weeks ago. Offline
Joined: 18 Nov 2011
Posts: 4
Groups: None

Why is that some people say: you can not use Physical percent complete on this schedule because it is not resource-loaded ?

As far as I know, Physical percent complete for the activities has nothing to do with the cost,except for calculation of WBS percent complete field which needs the cost and resource data.

can anyone help clear out this confusion?

Thank you

Replies

sadegh usman
User offline. Last seen 11 years 26 weeks ago. Offline
Joined: 12 Apr 2011
Posts: 4
Groups: None

This is confusing,but the basis of your physical % completion, can be check through cash % complete..their is discripancy but tolerable only..

Thanks,