Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to deal with Hangers/Out of Sequences/Activity changes?

3 replies [Last post]
Kandavel Raja P
User offline. Last seen 5 years 31 weeks ago. Offline
Joined: 29 Sep 2018
Posts: 2
Groups: None

Hi ... 

How to deal with "Out of sequences / Hangers" while tracking the project? I know how to find, but i just want to know how to fix it without changing the baseline end date?

Please note, ours a simple duration tracking project, without any resource/cost loading on it. Since we are not changing the end date, we dont require to do any RA & Stake holders approval. its a simple bug fixing. i would like to know how to correct it. 

Replies

Rafael Davila
User offline. Last seen 3 weeks 8 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Please take a look (click titles) at the following links:
  • Out-Of-Sequence Progress - Ultimately, it’s our recommendation that instead of relying on the Progress Override and Actual Dates options to deal with activities that progress out of sequence, owners should specify the use of the Retained Logic option and require contractors to address activities that progress out of sequence on an activity-by-activity basis as it occurs and to make appropriate changes to the schedule logic to ensure that the project schedule matches the current construction
  • Dangling Activities - In summary, the meaning of Mr. Hurst’s condemnation of “dangling activities” as per se improper CPM scheduling technique is clear and convincing when we consider the reality that the duration of activities cannot be estimated with certainty. 
Eric Uyttewaal
User offline. Last seen 5 years 31 weeks ago. Offline
Joined: 22 Dec 2017
Posts: 6
Groups: None

Kandavel,

An out-of-sequence updated hanger activity, as I understand it, is an activity that you made progress on ahead-of-its-scheduled-dates. By updating it, you should pull the Actual Start date to earlier, to before the Data Date (MS Project: Status Date). Since it is a 'hanger' activity, it does not have any successors and no other tasks will be affected by this updating. Entering the appropriate Actual Start date is the only thing you need to do at first glance.

On second sober thought, hanger tasks indicate an incomplete network of logic, so you should also find its rightful successor(s) and link these successor(s) up to it. It is not unthinkable that you have hard constraint dates on those tasks (that should not be there), which may pull back those activities as well. If these activities are o nthe Critical Path, the project will shorten, which may allow you to deliver your entire project early.

Hanger tasks should not exist; there can only be ONE hanger task in a schedule: the Project Finish milestone. 

In summary, there is a lot of things you should do:

1) Enter correct actual start

2) Find its successors and create these links

3) Check to verify if there are any inappropriate constraint dates on any of the successors, and, if so, remove them

4) Check your Critical Path to see what happened to it, if anything. If it shortened, then deliver early if you can.

Hope this helps! Thank you for this interesting question; there was more to it than I thought at first glance.

Zoltan Palffy
User offline. Last seen 8 weeks 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

this has NOTHING to do with chaning any dates.

out of secquence means just that. You started or completed  an activity sooner than the logic dictated ie.

activity A then Actvity B then Actvity C all tied together logically with finish to start relationships

[  A  ]------------------->[   B   ] -------------->[  C  ]    

for some reason you did NOT have to wait for B to finish before you could start or finish activity C

this is OUT OF SEQUENCE LOGIC this means that your original premis was incorrect or you just wanted to model it that way.

to correct this delete the relationship form B to C and make the relationship A to C. 

As far has hangers I am not sure of what you mean but if you mean activites that do not have relationships. There should bb no activities without succesors except the last one. If you need to tie the hangers into project completion or punch list or close out.