Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Data Date Explained...

3 replies [Last post]
S M
User offline. Last seen 2 years 37 weeks ago. Offline
Joined: 6 Oct 2012
Posts: 15
Groups: None

Hi Everyone,

I was wondering if anyone has a simple explanation of the Data date, what it is, what it's used for and how you would use a data date when you were updating a schedule weekly and updating a schedule monthly?

I'm aware of the data date I've just never found an exact, easy to understand definition and explanation of the concept.

I also need to pass this information on so would appreciate if I had a mastery of the subject matter first!

Thanks for your help,

Replies

Shah. HB
User offline. Last seen 49 weeks 1 day ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi<?xml:namespace prefix = o />

In addition to Vladimir Liberzon

 

1.Data Date is the reference date, to start the scheduling calculations (Forward/Backward Pass)

 

2.It is a Calendar date that separates actual (historical) data from future (scheduled) data

Johannes Vandenberg
User offline. Last seen 39 weeks 6 days ago. Offline
Joined: 21 Jan 2010
Posts: 234

Hi SM

I am running a website special dedicated to none planning professionals. These are engineers, production engineers, procurement officers, fabrication superintendents, fabrication supervisors, foreman and sometimes for project managers. I find often that the reading and understanding of Primavera schedules for none planning professionals is not as obvious as i would like. In order to meet the needs of better and more effective communication to the none planners i have launched this website. The site is now running for a year and a can already see that i have made good progress. Especially our production engineers and  fabrication supervisors and the foremen are now familiar with the schedules. The site was set-up for Dutch speaking people only but i have now translated a large part of the content in English.  I have also added a translate module for many other languages.

I here include a link to the website demonstrating the updating  and tracking of a resource loaded schedule in Primavera Suretrak. Here you can see the the Data date and the effect on the updating of the schedule and the tracking of the progress. I have made an baseline schedule and have updated and tracked progress for a period of 6 weeks. I have also included histograms and s-curves.

Here is the link

For the home  website Planning for none planners         http://plannenvoornietplanners.net/

Trust this is useful.

Regards

Johannes

Data Date is time up to which all information was updated.

Data Date shall be the same for all project elements (objects) before you will run project scheduling.