Data Date For Revised Target Plan

R
Razi Khan 👤 Member for 21 years 11 months
A
Alex Wong 👤 Member for 23 years 4 months

Some use the baseline schedule and update the logics, duration, additions, deletions and the same datadate as the revised target.



Otherwise as what Tahir suggested use the latest progressed schedule with all the additional information as your revised target.



HTH



ALex

T
Tahir Naseem PMP, CCE 👤 Member for 19 years 7 months

Dear Razi

Salam

The data date is the your cut of date of progress for six month.

But keep in mind you should copy your target first to save your original base line. And after update & revision of this current plan you will get your latest forecast plan can be use as target 2.

regards

tahir

Forum Sponsor

Top Posters

Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts