Data Date For Revised Target Plan

2 replies [Last post]
Razi Khan
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 17 Jun 2004
Posts: 74
Groups: None
Hi,

What would be the data date for establishing Revised Target Plan after of 6 month of progress ?



Cheers

Replies

Alex Wong
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Some use the baseline schedule and update the logics, duration, additions, deletions and the same datadate as the revised target.

Otherwise as what Tahir suggested use the latest progressed schedule with all the additional information as your revised target.

HTH

ALex
Tahir Naseem PMP,...
User offline. Last seen 6 years 1 week ago. Offline
Joined: 26 Oct 2006
Posts: 85
Dear Razi
Salam
The data date is the your cut of date of progress for six month.
But keep in mind you should copy your target first to save your original base line. And after update & revision of this current plan you will get your latest forecast plan can be use as target 2.
regards
tahir