Data Date For Revised Target Plan

Member for

22 years 9 months

Some use the baseline schedule and update the logics, duration, additions, deletions and the same datadate as the revised target.



Otherwise as what Tahir suggested use the latest progressed schedule with all the additional information as your revised target.



HTH



ALex

Member for

19 years

Dear Razi

Salam

The data date is the your cut of date of progress for six month.

But keep in mind you should copy your target first to save your original base line. And after update & revision of this current plan you will get your latest forecast plan can be use as target 2.

regards

tahir