Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Duration and Hours - Minutes

2 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 40 weeks 3 days ago. Offline

Hello All,

 

How would you represent Duration and Hours in Minutes.

 

If you want the duration to be 15 minutes what would we type it in hours 0.15H or the duration is 45 min = 0.45H

 

If we want a resource to work 1/2 an hour would we type 0.30H or if a resource is working for 45 min = 0.45H

 

A little confusing.

 

Thanks

Jithin

Replies

Zoltan Palffy
User offline. Last seen 1 week 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

go to edit users preference

click on the time units tab

under Unit of time make sure it says hour

under durations format change that to hour

then on the right under decimals make sure that is set to 2 decimals