Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Duration error - I entered days & it took it as hours.

2 replies [Last post]
Shishir Dhatwalia
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 18
Groups: GPC Qatar

I am new to P6 using P6v7.

I entered activities & their durations the normal way & added resources to the activities. It is showing like this: -

Original Duration Column as 20d [ fine as I entered 20 ]

Budgeted Units as 20h in Bottom Layout - Resources TAB. [ when i entered 20 as days, it took as hours]

This affected my Budgeted Total Cost Column, as my cost is taking the durations from the resources (in hrs.)

 

can anybody help, i guess some adjustment required in Preferences but i don t know where.

 

 

Replies

Shishir Dhatwalia
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 18
Groups: GPC Qatar

it worked 

thanks

Håkon Haukebøe
User offline. Last seen 5 years 27 weeks ago. Offline
Joined: 18 Sep 2012
Posts: 25
Groups: None

Try:

Edit - > user preferences - > Time units. There you can choose Units and Durations to Day.

 

Haakon