Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Overall vs Duration on Table Definition Dialog Box

5 replies [Last post]
Anu hans
User offline. Last seen 39 weeks 2 days ago. Offline
Joined: 13 Nov 2017
Posts: 14
Groups: None

I have created a column for Planned Percent Complete(PPC). When I opened the Table Definition Dialogue Box under Measure of Progress I can choose on drop down following options;

Duration

Overall

Cost

I'd like to know the difference when reporting progress between duration vs Overall please?

Replies

Anu hans
User offline. Last seen 39 weeks 2 days ago. Offline
Joined: 13 Nov 2017
Posts: 14
Groups: None

Thanks lot

Sanjib Pradhan
User offline. Last seen 4 years 28 weeks ago. Offline
Joined: 6 Jul 2007
Posts: 8
Groups: None

Overall Progress :  You may wish to enter and display progress as an overall percentage complete, a measurement that is independent of the duration of a task. For example, if a task is planned to take 10 days and 5 days have elapsed but only 20% of the task work has been done, you can record that the task is 20% overall complete, even though it is 50% complete when progress is viewed as a percentage of the task duration. Changes to the actual or remaining duration will not change the overall percentage complete value. Calculating progress in this way is most useful if you do not assign resources to your tasks. This progress is similar to P6 Physical Progress.

 

Sources : Power project help

Sanjib Pradhan
User offline. Last seen 4 years 28 weeks ago. Offline
Joined: 6 Jul 2007
Posts: 8
Groups: None
Source: Power Project Help: You may wish to enter and display progress as an overall percentage complete, a measurement that is independent of the duration of a task. For example, if a task is planned to take 10 days and 5 days have elapsed but only 20% of the task work has been done, you can record that the task is 20% overall complete, even though it is 50% complete when progress is viewed as a percentage of the task duration. Changes to the actual or remaining duration will not change the overall percentage complete value. Calculating progress in this way is most useful if you do not assign resources to your tasks. This progress is similar to P6 Physical Progress.
Anu hans
User offline. Last seen 39 weeks 2 days ago. Offline
Joined: 13 Nov 2017
Posts: 14
Groups: None

Thanks lot for your explanation