Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

1 day duration tasks

4 replies [Last post]
Craig Adams
User offline. Last seen 13 years 6 weeks ago. Offline
Joined: 11 Oct 2006
Posts: 71
Hello Fellow Planners,

Can anyone explain why 1 day duration tasks sometimes display starting and finishing on the same day then other one day tasks show to start one day finish the next?

Kind regards,

Craig Adams.

Replies

Vasilios Sarras
User offline. Last seen 8 years 20 weeks ago. Offline
Joined: 6 Jul 2010
Posts: 20
Groups: None

Thanks Mike.

Mike Testro
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Vasilios

There should be an Icon box that allows you to set your snap period.

You should also check Tools > Options > Progress and set the snapping unit to the same category.

Also got to Library Explorer and Time Units - here you can tick whatever time units you want to display in the Snap Dropdown.

Best regards

Mike Testro

Vasilios Sarras
User offline. Last seen 8 years 20 weeks ago. Offline
Joined: 6 Jul 2010
Posts: 20
Groups: None

Hi Mike,

Where can you find what your snapping unit is set to?

Kind Regards,

Vas

Mike Testro
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Craig

What is your snapping unit set to?

If it is set to Days then the duration will snap to the next day.

If it is hours then it will snap to the next hour.

If you have - say - an 8 hr work pattern but your 1 day work period is 7 hrs then the next task will start late in the afternoon of the same day.

Set your date format to show time as well as dates and you can see where things come adrift.

Having set your work pattern in the calendar make sure that the default setting (tools > default) is the same period.

Best regards

Mike Testro