Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Formula For Duration Between Tasks Based On Code Library Allocation

2 replies [Last post]
Chris Lothian
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 18 May 2007
Posts: 34

Hi All,

Following my last post (http://www.planningplanet.com/forums/asta-powerproject/537680/using-formula-answer-another-formula). I’ve realised I need help with the actual formula;

I have a programme with multiple tasks per line / bar, with each task on a line having a different code library allocation. The bars are set so that tasks may overlap.

I’m trying to get the duration (start to finish – not cumulative) between the start of a task with Code Library Allocation “A”, and the finish of a task with Code Library Allocation “D”. The tasks don’t appear at the same task number (in the line), so I don’t think I can use the task number object selection.

Code Library has object id 35

Code Library Allocation A has object id 167652

Code Library Allocation D has object id 167654

The formula that I’d got to is below, but although the status is OK, it doesn’t give the answer is was after;

DateDiff(Task.CodeLibrary(35, 0, 167652).Start, Task.CodeLibrary(35, 0, 167654).Finish)

 

I’ve tried since tried simplifying it in stages but they don’t seem to work either;

Should give the start of task code library allocation A (object id 167652).

Task.CodeLibrary(35, 0, 167652).Start

 

Should give the finish of task with code library allocation D (object id 167654);

Task.CodeLibrary(35, 0, 167654).Finish

Any help would be appreciated

Kind regards,

Chris

Replies

Chris Lothian
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 18 May 2007
Posts: 34

Thanks for this Chris, looks like i wasn't even close so would never have got there.

 

Chris Ray
User offline. Last seen 10 years 13 weeks ago. Offline
Joined: 23 Mar 2013
Posts: 3

Hi Chris,

I saw this question from the support team, the answer is as follows:

To get the formula to find the start date on a specific task with an assigned code library, you will need to check each task. the snippet below returns the start date of a task with a code library called "A" from the codelibary 'Default' ID 35

 

Switch(
Task[>1].TaskCodeLibrary(35, 0, na)="A",Task[>1].Start,
Task[>2].TaskCodeLibrary(35, 0, na)="A",Task[>2].Start,
Task[>3].TaskCodeLibrary(35, 0, na)="A",Task[>3].Start,
Task[>4].TaskCodeLibrary(35, 0, na)="A",Task[>4].Start,
Task[>5].TaskCodeLibrary(35, 0, na)="A",Task[>5].Start,
Task[>6].TaskCodeLibrary(35, 0, na)="A",Task[>6].Start,
Task[>7].TaskCodeLibrary(35, 0, na)="A",Task[>7].Start,
Task[>8].TaskCodeLibrary(35, 0, na)="A",Task[>8].Start)

 

You can then combine this with a search for the finish date in the same way and then perform a DateDiff on it.

(DateDiff(

(Switch(
Task[>1].TaskCodeLibrary(35, 0, na)="A",Task[>1].Start,
Task[>2].TaskCodeLibrary(35, 0, na)="A",Task[>2].Start,
Task[>3].TaskCodeLibrary(35, 0, na)="A",Task[>3].Start,
Task[>4].TaskCodeLibrary(35, 0, na)="A",Task[>4].Start,
Task[>5].TaskCodeLibrary(35, 0, na)="A",Task[>5].Start,
Task[>6].TaskCodeLibrary(35, 0, na)="A",Task[>6].Start,
Task[>7].TaskCodeLibrary(35, 0, na)="A",Task[>7].Start,
Task[>8].TaskCodeLibrary(35, 0, na)="A",Task[>8].Start))

,


(Switch(
Task[>1].TaskCodeLibrary(35, 0, na)="B",Task[>1].Finish,
Task[>2].TaskCodeLibrary(35, 0, na)="B",Task[>2].Finish,
Task[>3].TaskCodeLibrary(35, 0, na)="B",Task[>3].Finish,
Task[>4].TaskCodeLibrary(35, 0, na)="B",Task[>4].Finish,
Task[>5].TaskCodeLibrary(35, 0, na)="B",Task[>5].Finish,
Task[>6].TaskCodeLibrary(35, 0, na)="B",Task[>6].Finish,
Task[>7].TaskCodeLibrary(35, 0, na)="B",Task[>7].Finish,
Task[>8].TaskCodeLibrary(35, 0, na)="B",Task[>8].Finish))


))