Enclosed please find a link to a resource leveling test schedule as to compare how different software handle the resource allocation.
http://www.mediafire.com/view/u9s6qk45pjn9q6t/j3013_8_1.xml
I want to know the resulting duration but equally important the detailed resource usage plan as it is a requirement that all resources within each activity work together as a team and not at different times. Say one resource is a crane and another is a crane operator, you cannot schedule crane and crane operator at different times, this goes for all resources.
As I do not have Asta PP I am enclosing the schedule in MS Project XML format so you can import it and run the resource leveling. In order for those of us not having Asta PP we need you post the resulting resource distribution in PDF. I downloaded the free viewer but not sure if it will work, the Asta PP file will also be welcomed.
Replies