Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Word

Project Manager, Nanometrics Inc., Semiconductor tool product portfolio

START Date: 
January, 2007
END Date: 
October, 2012

Implemented Microsoft Project Server to connect remote engineering teams and balance resource usage and availability globally.

Developed a SharePoint application for engineering Change Control with approval workflow

Created and maintained project plans for hardware (waterfall) and software (Agile)

Administrated Team Foundation Server to enable software development etams to self organise and manage

Managed project plans using MSP 2007/2010 and Project Server 2007/2010

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1100
Experience Hours (Forensic Analysis): 
1600

Project Planning Engineer with 3 year(s) Exp in MEP,HVAC & EPC. B.Tech (ME),MS Project ,Primavera,Project Management., ETA Engineering Pvt Ltd, District Cooling Plant, Gift City (EPC Project).

START Date: 
July, 2012

ÈPreparation of Baseline Program for project at the tendering stage as per the scope of work using Primavera 6.

ÈDeveloped the (MTS) level 4 integrated EPC (Engineering, Procurement and Construction) schedule based on contract requirements in cooperation with the Managing Contractor on Primavera

ÈComplete resource planning including labour & non labour (Machinery) as per project scope using productivity norms.

Experience Hours (Planning & Scheduling): 
3400
Experience Hours (Cost Management): 
900

Planning Engineer, Qatar Power Construction W.L.L, Electricity Distribution Network

START Date: 
November, 2011

Planning Engineer for Electricity Distribution Network project for the general body for Water and Electricity of the State of Qatar.

Scope of Work Includes :

-Preparing schedule of Electrical and Civil works.

-Progress and Cost Monitoring.

-TIA and Claims.

Estimator / Quantity Surveyor, Saudi Oger Ltd., kAP # 1

START Date: 
September, 2012
END Date: 
October, 2005

 

Particulars of Work experience:

Seven years of experience in Quantity Surveying on Construction of fast track Project’s executed by well known Company. 

Estimator / Quantity Surveyor, Saudi Oger Ltd., kAP # 1

START Date: 
September, 2012
END Date: 
October, 2005

 

Particulars of Work experience:

Seven years of experience in Quantity Surveying on Construction of fast track Project’s executed by well known Company. 

Construction Site Superintendent (Paving), Bechtel Co. Inc. & Enka Co. Inc. General Partners, Kosovo, Kosovo Motorway Project

START Date: 
March, 2011
END Date: 
January, 2012
  • Directed and managed all paving operations with overall responsibilities for safety, production, maintenance, quality and other production-related activities.
  • Oversaw the production planning, staffing, and day-to-day paving operations in a cost-effective manner.
  • Prepared paving schedule and coordinated production activities to ensure production and quality of products meet specifications.
  • Worked closely with Quarry & Plants department to ensure mat

Project Planner, BLACK & VEATCH International, 1.Refurbishments[Design, Supply, Installation, Construction, commissioning and testing] Lane End WTW [3 million Pound starlings],2.Refurbishments[Design, Supply, Installation, Construction, commissioning and

START Date: 
June, 2007
END Date: 
December, 2008

Responsibilities discharged   

  • Develop the Schedule, Set up the base line
  • Resource loading, Target setup
  • Coordinate with project team
  • Attain the meeting and follow the guideline and Collect the data from project
  • Monitoring the Sub contractor works and update the Schedule accordingly
  • Update the schedule and analysis the Current float and critical path.
  • Advice the project manager for critical activities and concern cause.
  • Produce Monthly Project Fina

Project Planner, ABB Ltd, 1.Replacement of Wakefield B 132 kV GIS – 15 Million GBP [ Client CE Electric ], 2.Walpole 132 kV GIS, SGT5 and Centrica Bas Bar Extension – 35 Million GBP [ Client National Grid]

START Date: 
January, 2009

 

Project Planner/Mechanical Engineer

(17 years experience)

 

  • Prepared, maintained and monitored project plans/schedules.
  • Significant skill on Planning Tools [ Primavera P3 version 3.1,Microsoft Project]
  • I got training on Planning Tools P6 and currently working on P6.
  • Performed critical path analyses, earned value analyses, resource leveling.
  • Involved with site planning in terms of programming and progress monitoring.
  • Worked / lia

Senior Planner / Tender Planner, Sir Robert McAlpine Ltd, Tenders and Advice

START Date: 
August, 2015
END Date: 
August, 2016

Primavera, Power Projects, MS Project, Excel, Word, Airports, Tunnels, Roads, Bridges, Sewage Works, Hospitals, Shoping Centres, Rail, Offices, Highrise, Apartments

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Forensic Analysis): 
200

Market Place

No results found... (try selecting a different content filter)

Syndicate content