Project Planning ,Project Management ,Project Execution,Mechanical Engineer,Project Control Engineer, Ms Project 2010 Professional, Primavera p6, ERP, MS Excel, MS Word, MS Power Point, AutoCad,,MEP,HVAC,EPC,Scheduling,District Cooling Plant.
ÈPreparation of Baseline Program for project at the tendering stage as per the scope of work using Primavera 6.
ÈDeveloped the (MTS) level 4 integrated EPC (Engineering, Procurement and Construction) schedule based on contract requirements in cooperation with the Managing Contractor on Primavera
ÈComplete resource planning including labour & non labour (Machinery) as per project scope using productivity norms.
Posted Sun, 2013-09-08 18:27 by vidyadhar bhojaraj
START Date:
April, 2009
END Date:
September, 2010
Estimation and costing for MEP activity and preparation of proposal by clearly studying the tender document like specification, Drawing and tender conditions.
Preparation of Job Cost analysis and controlling the cost during the procurement of material.
Identifying the extra item and submitting the variation proposal for the approval.
Preparation of monthly bill and measurement sheet as backup document.
Preparation of MEP baseline program and procurement of material as per the project schedule.