Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Primavera P3. Primavera P6

Planning and Project Control Chief Engineer, Snamprojetti and Persian Gulf Oil Company Consortium, Persian Gulf Oil Refinery

START Date: 
February, 2008
END Date: 
November, 2011

 

  • Scope definition of project in a EPC contract as a master scheduler
  • Consult with PM to bring fall behind project back on track
  • CPM scheduling, resource leveling, EV, SP, CP, TCPI, VAC and ETC calculation
  • Development of project planning and monitoring procedures and systems
  • Involve in project management office process and coordination
  • Project prediction based on analyze schedule progress and performance
  • Engineering and Construction coordinator
  • Associate with change order evaluations team and analyze r

Site Planning and Project Control Engineer, Foster Wheeler, GS, OIEC COnsortium, South Pars Gas Field, Phases 9 & 10

START Date: 
April, 2004
END Date: 
January, 2008
  • Site scheduler and project controller
  • Work with construction crew in order to prepare work front and look ahead plan
  • Assist with scheduling team to estimate and calculate activities duration and physical progress
  • Accomplishment as a qualified planner to reduce disordering between sub-contractors
  • Assist with PMO in fast tracking plans, catch up plans  preparation
  • Data gathering from construction team to prepare project progress reports
  • Update and Progress data bank to monitor the EPC versus baseline through S-curves

Project Planner, BLACK & VEATCH International, Waste and clean water Treatment

START Date: 
June, 2007
END Date: 
December, 2008
  1. Refurbishments[Design, Supply, Installation, Construction, commissioning and testing]  Lane End WTW [3 million Pound starlings]

            Clients:Thames Water

  1. Refurbishments[Design, Supply, Installation, Construction, commissioning and testing]  

     Ashford STC [12 Million Pound starlings]

     Clients: 4 D

  1. pH Correction

Project Planner, BLACK & VEATCH International, 1.Refurbishments[Design, Supply, Installation, Construction, commissioning and testing] Lane End WTW [3 million Pound starlings],2.Refurbishments[Design, Supply, Installation, Construction, commissioning and

START Date: 
June, 2007
END Date: 
December, 2008

Responsibilities discharged   

  • Develop the Schedule, Set up the base line
  • Resource loading, Target setup
  • Coordinate with project team
  • Attain the meeting and follow the guideline and Collect the data from project
  • Monitoring the Sub contractor works and update the Schedule accordingly
  • Update the schedule and analysis the Current float and critical path.
  • Advice the project manager for critical activities and concern cause.
  • Produce Monthly Project Fina

Senior Planning Engineer, Nagarjuna Oil Corporation Limited, Cuddalore Refinery Project

START Date: 
January, 2006
  • Project monitoring and Coordination with EPCM, PMC (CB&I lummus), EPC and Construction contractors.
  •  Preparing of overall project schedule using primavera 6

Market Place

No results found... (try selecting a different content filter)

Syndicate content