Head of Projects Planning & Control and Database Section, Petrobel (EGPC/ENI/BP), Oil and Gas On/Offshore development program of various sized projects

START Date: 
January, 2009
END Date: 
July, 2011

 

Head of Projects Planning & Control and Database Section

Petrobel Egypt (Oil & Gas Client/ENI & BP) – Cairo Head Office

 

The mission was to run & monitor the projects control system for a program of various sized On/Offshore Oil & Gas Projects respecting the shareholders targets & the company rules & procedures, the job responsibilities were mainly the following:

Lead Planning Engineer, Siemens Transmission & Distribution, Gwynt-y-Mor Offshore Wind Farm

START Date: 
August, 2009
END Date: 
July, 2011

Gwynt-y-Mor Offshore Wind Farm

Responsible for preparation of Level 2 & 3 cost loaded programmes, “S” Curves and Earned Value measurement for a £120m wind farm off the coast of North Wales.

Greater Gabbard Offshore Wind Farm

Programme and Project Control Manager, Sanyati (South Africa), Company wide

START Date: 
January, 2005
 
 
 
  • The Programme & Project Controls Manager is a senior business unit manager position within Sanyati.

Project co-ordinator, Bombardier Transportation, Connex 376, Victoria line upgrade LUL

START Date: 
January, 2002
END Date: 
March, 2005

Project co-ordinator - working within the engineering department for the design and manufacturing of the Rail vehicle carbody. Duties include scheduling the workload, resource management, progress reporting, recovery programmes, communication of issues to project management. This role also involved some international travel to other sites.

Project Planner, Bombardier Transportation, SSL (Sub surface lines) London Underground

START Date: 
March, 2005
END Date: 
September, 2008

Lead project planner reporting to the project control manager Bombardier Transportation within London Underground Projects Division. Rolling stock and signalling integrator. Role involved managing all programme matters for the Sub Surface line contract for the delivery of 1300 underground vehicles and the re signalling of the applicable lines of London Underground.

Project Planner, Bombardier Transportation, LERL, SBB, Southern

START Date: 
September, 2008

Currently a project planner within the engineering/ design department at Bombardier Transportation (rolling stock and systems integrator) train design and manufacturing company. Developing programmes to deliver the design/engineering of rail vehicles usually to very tight timeframes. Manage programme for engineering team for the LERL project for new vehicles to operate from Stansted. This project was a significant amount of man hours and a two year duration from project start to first vehicle into service. This project was successfully delivered on time.

Project Controls Engineer, Balfour Beatty Civil Engineering, T2B Heathrow

START Date: 
June, 2011
END Date: 
April, 2013

06/2011 – Present           Balfour Beatty Major Civil Engineering -               Project Controls Engineer: Fit Out

Balfour Beatty Group is constructing Heathrow Terminal 2B as part of the reconstruction of Terminal 2 which has been demolished. The Terminal 2 project consists of 3 phases A, B & C of which I am employed on Phase B as part of the Project Controls team which consists of 5 Engineers.

Project Cost Controller, Thales Australia, JP2070 Project Djimindi Alliance Lightweight Torpedo Project

START Date: 
August, 2002
END Date: 
October, 2005
• Maintenance of the project Performance Measurement Baseline. • Maintenance of the Cost/ Schedule Control System documentation, including Earned Value Management and Scheduling. • Develop and maintain the Earned Value System Description and Earned Value Management Plan in conjunction with the Project Scheduler. • Collect monthly Earned Value progress from Control Account Managers and Alliance partners. • Preparation of monthly Cost Schedule Status Reports using Cobra Cost Processor. • Analysis of project performance using Earned Value methodologies. • Participation in Integrated Baselin

Lead Planner, National Nuclear Laboratory, NEXIA Solutions, Legacy Ponds and silos

START Date: 
February, 2005

I'm a highly motivated Lead Planning Engineer with six years planning and costing experience at the National Nuclear Laboratory (NNL). A well-respected and qualified team member who consistently works to the highest standard and thrives when working as part of a project team. A conscientious, driven performer who develops future procedures at NNL and mentors new members of staff.

 

Major Achievements

 

Senior Engineer, Planning/Project Controls, Evonik Energy Services India, Power Plants - Head Office Various Projects

START Date: 
March, 2010
  • Plan projects from inception to completion; besides handling construction activities.

 

  • Develop schedule of activities, resource planning, project budgeting; monitor project progress and generate variation report for management.

 

  • Utilize Primavera in the preparation of schedule of activities

 

  • Development of Project Measurement Methodology and Tools for Engineering, Procurement and Construction

 

  •  Progress reporting in terms of performance indi