06/2011 – Present           Balfour Beatty Major Civil Engineering -               Project Controls Engineer: Fit Out

Balfour Beatty Group is constructing Heathrow Terminal 2B as part of the reconstruction of Terminal 2 which has been demolished. The Terminal 2 project consists of 3 phases A, B & C of which I am employed on Phase B as part of the Project Controls team which consists of 5 Engineers.

Key Responsibilities & Achievements

§  Responsible for the entire Internal Fit-Out of Terminal 2B which involves the monitoring and reporting on 19 subcontractors working on the Fit Out phase of the project

§  Developed agreed schedules for each subcontract with the Planning & Commercial teams along with the Construction Managers used for the Earned Value Analysis and Reporting each period

§  Developed KPIs for each subcontract to monitor progress and as an input to the Earned Value reports each period along with daily progress reports to senior management and the client

§  Presenting Earned Value data to senior management each period for approval prior to client presentations

§  Responding to client queries at monthly Q&A sessions

§  Reconciling costs and forecasts with Commercial Managers between the commercial accounts and Earned Value Analysis costs and forecasts