JP2070 Project Djimindi Alliance Lightweight Torpedo Project

Project Cost Controller, Thales Australia, JP2070 Project Djimindi Alliance Lightweight Torpedo Project

START Date: 
August, 2002
END Date: 
October, 2005
• Maintenance of the project Performance Measurement Baseline. • Maintenance of the Cost/ Schedule Control System documentation, including Earned Value Management and Scheduling. • Develop and maintain the Earned Value System Description and Earned Value Management Plan in conjunction with the Project Scheduler. • Collect monthly Earned Value progress from Control Account Managers and Alliance partners. • Preparation of monthly Cost Schedule Status Reports using Cobra Cost Processor. • Analysis of project performance using Earned Value methodologies. • Participation in Integrated Baselin