Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Commissioning

VP of Learning & Development, IACE, Development of International Association of Commissioning Engineers Development materials

START Date: 
June, 2015

I am an experienced Project management professional.   I work both as project manager or project consultant and work closely with Project controls.   Delivering training where required, including the ECITB City & Guilds NVQ in Project Controls. 

 

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
600

Senior Planner, Mott MacDonald, Essex Waste MBT

START Date: 
December, 2013
END Date: 
January, 2014

Project Description

New build Mechanical & Biological Treatment (MBT) plant to process circa 500k tonnes of household waste in Essex, UK.

 

Role and Responsibilities

Experience Hours (Planning & Scheduling): 
300

SR. INSTRUMENT TECHNICIAN ( COMMISSIONING ), ESTRAN BECHTEL COMPANY, ASAB GAS PROJECT II ABHUDHABI, UAE

START Date: 
December, 2009
END Date: 
June, 2010

ESTRAN BECHTEL COMPANY

   ASAB GAS PROJECT II

    ABHUDHABI, UAE.

   29/DEC/2009 TO 24/JUNE/2010

   POSITION : SR. INSTRUMENT TECHNICIAN ( COMMISSIONING)

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
1000

Project Control Manager/ Forensic Planner, STRABAG, Pabianice Express Road Bypass S14

START Date: 
December, 2008
END Date: 
April, 2012

Setting the Contractor strategy ant the contracting politics.

Claims and Variation manageing

Planning and Scheduling in MS Project & Asta Power Project.

Setting the main assumptions for critical path and technological procedures for Time Schedule, ongoing verifiation and adaptation.

Contractor representation in front of Employer and Engineer.

Controling the on-site activity in accordance to signed Contract, Building Law, Public Procurement Law and Common Law.

FIDIC General Condidtion guiding and approach to all on site activity

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Forensic Analysis): 
4000

Commissioning Planner, BLACK & VEATCH International, Kusile Power Plant

START Date: 
October, 2013

4800MW Supercritical Coal Fired Power Plant

Resposible for:

Commissioning & Startup Planning,

Progress Measurement,

Subcontractor's schedule coordination,

Interface Management,

Schedule Risk Analysis,

Outage Planning,

Manager Technical, Alexandria Fiber Co. S.A.E.Egypt, Alexandria Fiber Co. S.A.E., Egypt

START Date: 
March, 2004
END Date: 
April, 2007

MANAGER (TECHNICAL CELL)

·         AFCOis established in 2004 and I am working in its gross root stage. It is a group company of ADITYA BIRLA GROUP.

·         Main Responsibilities include with purchase activities related to chemical area, Water treatment and Effluent treatment plants.

Project Manager / Planner, J. Brand Ltd., Multiple Power & Data Network Installations

START Date: 
June, 2000
END Date: 
September, 2007

Project Manager/Planner. Smaller value, multiple location, simultaneous projects. Encompassing All project activities, form proposals, procurement, planning (activity & resource) and coordination of multiple project locations throughout the UK.

Commissioning & Startup Planner, Primavera P3, MARATHON OIL, ALBA Gas Plant

START Date: 
January, 2003
END Date: 
January, 2005

Responsible for the development of a system-based commissioning and start-up plan for a new Gas Plant in EG. The first stage included Power Generation, Gas Compression and Injection packages along with associated utilities (Flare, Drains, Air and Utility Water etc). The second stage involved commissioning of a new Gas Plant and LPG Storage tanks.

 Commissioning activities were resourced to provide manning requirements and progress reports by manhours.

Planning Engineer, BNFL (Sellafield Sites), THORP Nuclear Plant

START Date: 
July, 1990
END Date: 
March, 1991

Responsible for the control and monitoring of several contractors programmes and for integrating them into an overall construction programme.

Development of a Sub Station cabling and commissioning programme to provide phased electrical start up to meet the overall THORP plant commissioning programme.

Software used was Artemis 2000 and SMART integrated package for general reporting.

Senior Planner / Scheduler, Queensland Energy Resources Pty Ltd, Technology Demonstration Plant for Shale to Liquids Industry

START Date: 
May, 2009

A Sennior Planning and Scheduling Engineering Speciallist with the Oil and Gas Sector with over 15 years of professional engineering experience in both Engineering and Construction.

Market Place

No results found... (try selecting a different content filter)

Syndicate content