PMO Project Controls Manager, Wadi Degla Energy Projects, 1 x 20 MW Solar power project at Benban, Aswan, Egypt

START Date: 
January, 2015
END Date: 
June, 2017

Created, maintained & tracked resource & cost loaded schedules for 20 MWac & 2.5 MWac PV solar projects with a cumulative value of $42+ million. Developed & maintained a cost/schedule control system to provide the required guidance & support the project with the decision-making tools for project control. Performed CPM & EVM analysis & generated status, resource & cost reports with best practices recommendations for senior management.

Experience Hours (Planning & Scheduling): 
4800
Experience Hours (Cost Management): 
2400

Project Planning Manager, Sterling & Wilson Pvt Ltd, 5 X 50 MW solar power project in Benban, Aswan, Egypt

START Date: 
October, 2018

Successfully manage 5 planning engineers to prepare & update the schedules of 5x50 MWac (322 MWp) PV solar projects for 5 well-known clients (General Electric, TAQA Arabia, Shapoorji Pallonji, EDF, & El Sewedy). Manage the submission of timely daily, weekly & monthly progress reports to clients. Manage the preparation of internal plans & lookaheads. Discuss & follow up the execution of these plans with projects stakeholders including, but not limited to, SWPL engineering, procurement/logistics, construction, subcontractor, & management teams.

Experience Hours (Planning & Scheduling): 
1350

planning engineer, (AL Said for Consulting Engineering),egypt, Intake, booster and pipelines of 10th Ramadan water treatment plant,egypt

START Date: 
May, 2012
END Date: 
April, 2013

(AL Said for Consulting Engineering),cairo,egypt


Title: Project management engineer (Planner-Time & Cost control): planning and follow up tasks (time schedule, resource definition and allocation, cash flow, follow the progress and readjust according to the actual performance.

Manager Technical, Alexandria Fiber Co. S.A.E.Egypt, Alexandria Fiber Co. S.A.E., Egypt

START Date: 
March, 2004
END Date: 
April, 2007

MANAGER (TECHNICAL CELL)

·         AFCOis established in 2004 and I am working in its gross root stage. It is a group company of ADITYA BIRLA GROUP.

·         Main Responsibilities include with purchase activities related to chemical area, Water treatment and Effluent treatment plants.

Construction Project Controls/Planning Engineer, orascom HD, El Gouna , Egypt

START Date: 
November, 2008
END Date: 
August, 2012

i worked on OHD as a project control in el Gouna City for 4 years controlling the progress and fo=inish dates targets

Site Engineer, Alex. Construction Company (A.C.C) - Talaat Mostafa - Egypt, Water Desalination planet - Montazah Center - Sharm El-sheikh, Egypt

START Date: 
October, 1996
END Date: 
July, 1999

Water Desalination planet - Montazah Center - Sharm El-sheikh, Egypt

Construction of "Water Desalination planet ", the skeleton of tow elevated tanks & 4 Underground tanks, the pump station, the infra-structural works, the Hardscape & Landscape Works & Internal and External Roads & Finishing Works and Handing over the Project.

Senior Planning Engineer, ORASCOM CONSTRUCTION INDUSTRIES (OCI), 2000 MTPD KAAP Ammonia Plant, Suez Industrial Zone, Egypt

START Date: 
March, 2006
END Date: 
August, 2006

2000 MTPD KAAP Ammonia Plant, Suez Industrial Zone, Egypt

The Scope of this subcontracted work shall consist of providing all items necessary to provide satisfactory completion of construction services (Temporary Construction Facilities and Services, Civil Works, Structural Steel Erection, Pipe Fabrication Execution Plan, Underground Piping, Aboveground piping, Architectural works, Mechanical Works, Electrical works Instrumentation works, painting works and insulation works) pertaining to the EBIC 2000 MTPD KAAP Ammonia Plant Project, located in the Suez Industrial Development Area,

Business Development Deputy Manager, Ginza Construction, Head Office, Egypt

START Date: 
June, 2004
END Date: 
August, 2006

Business Development, Strategic Planning, Global Tendering, Client Relations, Tendering Overlook

Senior Planning Engineer, PMO ( Bechtel- GPP), City Stars, Cairo, Egypt

START Date: 
October, 2002
END Date: 
March, 2004

Senior Planner:

- Project schedule review

- Progress review and analysis

- VO time impact  analysis

- Claim review and time impact analysis

PLANNING ENGINEER, Kvaerner / Skanska, New Media Production City in Cairo, Egypt

START Date: 
July, 1999
END Date: 
October, 2001

New Media Production City in Cairo, Egypt

Duties include all aspects of Construction Planning, Design & Procurement Planning & Cost Control, Progress monitoring, and Resource Scheduling from structure to Building Finishes inc. M&E and Commissioning.