%100- Project Planning; Progress Reporting; Primavera P6; project cont

Lead Planning & Control Engineer, BP, BP Engineering Functions

START Date: 
July, 2010
END Date: 
December, 2013

Activity Planning Functional Lead responsible for the implementation of an integrated planning system utilising Primavera P6, Maxivera and Maximo planning software.

Training of Azrbaijan nationals in the use of the system

Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
500

Project Planner, Network Rail, IP Central Region Programme Compliance

START Date: 
April, 2015
END Date: 
October, 2015

Contract Project Planner for Network Rail IP Central Region team, assisting with central planning functions, particularly the managing and monitoring of Signal Tester and OLE resource demands for critical Bank Holiday works and programme compliance with the IP Central 6 year Plan and the Signalling Team's Commissioning Diary.

Experience Hours (Planning & Scheduling): 
1000

Senior Planner, Colas Rail, Kent & Sussex platform extensions (joint venture with Morgan Sindall)

START Date: 
November, 2010
END Date: 
December, 2013

Colas Rail                                                                                                   

Construction Project Planner / Senior Planner, Permasteelisa Qartner Qatar, NDIA- New Doha International Airport- Terminal Complex Lounges

START Date: 
March, 2016

 -  Prepares baseline program with coordination from technical and project manager.

 -  Prepares manpower/equipment histogram and progress s-curve.

 -  Direct & supervise junior planners in preparing progress monitoring/reports.

 -  Prepares schedule impact analysis.

 -  Prepares contractual progress report.

Experience Hours (Planning & Scheduling): 
22200

Construction Project Planner / Senior Planner, Permasteelisa Qartner Qatar, NDIA- New Doha International Airport- Terminal Complex Lounges

START Date: 
March, 2016

 -  Prepares baseline program with coordination from technical and project manager.

 -  Prepares manpower/equipment histogram and progress s-curve.

 -  Direct & supervise junior planners in preparing progress monitoring/reports.

 -  Prepares schedule impact analysis.

 -  Prepares contractual progress report.

Experience Hours (Planning & Scheduling): 
22200

Construction Project Planner / Senior Planner, Permasteelisa Qartner Qatar, NDIA- New Doha International Airport- Terminal Complex Lounges

START Date: 
March, 2016

 -  Prepares baseline program with coordination from technical and project manager.

 -  Prepares manpower/equipment histogram and progress s-curve.

 -  Direct & supervise junior planners in preparing progress monitoring/reports.

 -  Prepares schedule impact analysis.

 -  Prepares contractual progress report.

Experience Hours (Planning & Scheduling): 
22200

Construction Project Planner / Senior Planner, Permasteelisa Qartner Qatar, NDIA- New Doha International Airport- Terminal Complex Lounges

START Date: 
March, 2016

 -  Prepares baseline program with coordination from technical and project manager.

 -  Prepares manpower/equipment histogram and progress s-curve.

 -  Direct & supervise junior planners in preparing progress monitoring/reports.

 -  Prepares schedule impact analysis.

 -  Prepares contractual progress report.

Experience Hours (Planning & Scheduling): 
22200

Area Planning Manager, Skanska, AMP6 Capital Delivery Alliance

START Date: 
January, 2015

Planning Manager responsible for a small team of planners, delivering complex Infractructure and non-infrastructure projects across the Clean and Waste workstreams within the AMP6 Capital Delivery Alliance with Welsh Water. 

Area Planning Manager, Skanska, AMP6 Capital Delivery Alliance

START Date: 
January, 2015

Planning Manager responsible for a small team of planners, delivering complex Infractructure and non-infrastructure projects across the Clean and Waste workstreams within the AMP6 Capital Delivery Alliance with Welsh Water. 

Project Controls Manager, TURNER AND TOWNSEND, Subway Modernisation

START Date: 
May, 2015

 - Implement Project Planning & Scheduling strategy, plans and procedures, reflecting both Company and contractor roles, responsibilities and expectations.

Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
8000
Experience Hours (Forensic Analysis): 
200