Project Controls Manager, TURNER AND TOWNSEND, Subway Modernisation

START Date: 
May, 2015

 - Implement Project Planning & Scheduling strategy, plans and procedures, reflecting both Company and contractor roles, responsibilities and expectations.

 - Coordinate the development and implementation of project Work Breakdown Structures (WBS) and Cost Breakdown Structures (CBS) in concert with Project Lead, Project cost engineer and contractor project controls leads, and in conjunction with Project Execution Plans. - Promote and maintain the overall integration and integrity of contractor schedules within the Program suite of project schedules. -  Provide interface and quality assurance to Project functional groups and contractors regarding the tracking and reporting of schedule performance. - Support the Project Team in the implementation of an integrated enterprise based, cross functional and EPC master schedule program. - Conduct the required project schedule analysis, critical path analysis and schedule risk analysis for the project as a whole. - Analyse deviations from the baseline in the Project schedule highlighting bottlenecks / delays and propose corrective actions. - Prepare the Integrated Planning / Scheduling contribution to the Monthly Project Report and specific reports / presentations. - Analyse and highlight the overall schedule impact of any variance / change order. - Support the preparation of resourcing plans for the overall and individual project phases, identifying any excessive peak numbers and making recommendations for peak levelling.Working closely with various disciplines in project teams to ensure the accuracy and completeness of the schedules produced without compromising independence as a planning engineer 
Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
8000
Experience Hours (Forensic Analysis): 