Revision of Planning Terms from Tue, 2010-06-15 00:37

Normal 0 false false false EN-US X-NONE X-NONE MicrosoftInternetExplorer4 /* Style Definitions */ table.MsoNormalTable {mso-style-name:"Table Normal"; mso-tstyle-rowband-size:0; mso-tstyle-colband-size:0; mso-style-noshow:yes; mso-style-priority:99; mso-style-qformat:yes; mso-style-parent:""; mso-padding-alt:0in 5.4pt 0in 5.4pt; mso-para-margin:0in; mso-para-margin-bottom:.0001pt; mso-pagination:widow-orphan; font-size:11.0pt; font-family:"Calibri","sans-serif"; mso-ascii-font-family:Calibri; mso-ascii-theme-font:minor-latin; mso-fareast-font-family:"Times New Roman"; mso-fareast-theme-font:minor-fareast; mso-hansi-font-family:Calibri; mso-hansi-theme-font:minor-latin; mso-bidi-font-family:"Times New Roman"; mso-bidi-theme-font:minor-bidi;}

Critical path DRAG (Devaux’s Removed Activity Gauge) is a new scheduling metric in critical path analysis [http://planningplanet.com/wiki/index.php?q=35/critical-path-method].  It is the amount of time that an activity on the critical path [http://planningplanet.com/wiki/index.php?q=220/critical-path] (i.e., the longest path through the project) is adding to the project’s duration or, alternatively, the amount of time by which the project completion would be pulled in by reducing a critical path activity’s [http://planningplanet.com/wiki/index.php?q=219/critical-activity] duration to zero. 

Activities that are not on the critical path are said to have total float [http://planningplanet.com/wiki/index.php?q=37/total-float] or slack, i.e., the amount of time they can slip without making the project longer.  Conversely, only critical path activities and delays (such as lags or constraints [http://planningplanet.com/wiki/index.php?q=28/constraint]) have DRAG.   

  1. DRAG can be computed in the following manner:
  2. If an activity has nothing in parallel, its DRAG is equal to its duration.

If an activity has other paths in parallel, its DRAG is whichever is less: its duration or the total float of the parallel activity with the least total float.

There are three commercially avaliable software packages that compute DRAG:

  • Spider Project.
  • PlanontheNet.com
  • Sumatra.com's Project Optimizer, which ias an add-on to Microsoft Project.

DRAG has a corollary cost effect called DRAG Cost [http://planningplanet.com/wiki/index.php?q=35/DRAG-Cost], which is the amount by which project profit is decreased due to an activity’s DRAG reducing the value of the deliverable and/or increasing project cost through indirect costs attached to level-of-effort activities or overhead.  