PLANNING ENGINEER

PLANNING ENGINEER, "Al Naboodah Contracting LLC, Dubai", AX 124 D, AX 415, AX 457, AX124 A, JXB 010

START Date: 
May, 2007
END Date: 
August, 2009

·      Prepare target programs. Address the correspondence related to program / progress with client, consultant &sub-contractors.

·      Preparation of planning and scheduling documents such as, updated master schedules, progress reports, ‘S’ curves and Bar charts etc.

1.“planning engineer” or “project planner”, 1st Call Construction Pty Ltd, Civil Projects

START Date: 
January, 2003

Updating Planning database.
Preparing planning data.

Schedule development.

Project tender analysis.

Construction Sequence Analysis

Planning Engineer, Gulf Technical Construction company LLC, Multi Projects

START Date: 
March, 2008

Roles and Responsibilities:

·         To produce Resource and Cost loaded Baseline and recovery programs for various projects in Dubai, Abu Dhabi and Saudi Arabia.

·         To produce Tender programs for various projects in UAE, Saudi Arabia and Libya,

·         To produce company’s cash in-flows and out-flows periodically,

PLANNING ENGINEER, AMEC, Sellafield

START Date: 
January, 1997
END Date: 
November, 2000

Various overhauls of petrochemical plants in the North West UK.
Transferred to Reprocessing plant in Cumbria on a new build and also took on existing projects whilst based there

Planning Engineer, Petrojet (Egypt), Betreco Crude Oil Development Plant

START Date: 
December, 1995
END Date: 
May, 1997
  • Preparing the overall project detailed schedule.
  • Preparing & following up look-ahead construction plans.
  • Daily, weekly, and monthly follow up of projects through relevant reports.
  • Control and coordinate all assignments related to planning and reporting.
  • Analyzing delay reasons if occurred and participating in planning the best ways to overcome such reasons.
  • Preparing & following up the manpower productivity reports depending on the scheduled figures.
  • Following up, updating & revising the project schedule.
  • Following up
Experience Hours (Planning & Scheduling): 
3400

PLANNING ENGINEER, Enrichment Technology UK ltd., Uranium Enrichment Plant New Build

START Date: 
August, 2000
END Date: 
September, 2008

Enrichment Technology UK Ltd., (formerly URENCO), Capenhurst

Planning Engineer

Responsible to the Project Manager for the Level 1 Strategy and Construction and Installation Programmes, and Level 2 and 3 Integrated Construction Programmes for the Design, Construction, M&E Installation and Commissioning & Hand over phases of a “new build” uranium enrichment plant project in Europe. 3 years experience working on Urenco’s Dutch project and latterly based on the Capenhurst project near Chester.

Experience Hours (Planning & Scheduling): 
16150
Experience Hours (Cost Management): 
8050

Planning Engineer, Al Futtaim Group Real Estate, Dubai Festival City

START Date: 
September, 2006
END Date: 
December, 2008

Job Profile     :     
     Analysis, monitoring and assessment of contractors Programme of works and Reports.
     Analyse critical works and perform what-if analysis on contractors programme.
      Identify and monitor project risks and generate programmes of worst case scenarios for risk management.
     Analysis, monitoring and assessment of contractors Extension of Time Claims.

Planning Engineer, North East Shipbuilders Ltd., (various projects)

START Date: 
August, 1984
END Date: 
July, 1988

Responsible for unit outfit work packages for all production areas. Modular pipe work systems were split into work package information to enable 50 tonne modules of pipe work to be assembled offsite and then be installed as a complete unit. Also 500 tonne accommodation units were work packaged in a similar manner and fabricated on the quayside and lifted upon the vessel as a complete finished unit. Work packaging of this nature was developed during the construction of the I.T.M. "Challenger" which is a 45,000 tonne Crane Ship - the largest of its type in the World.

PLANNING ENGINEER, ETA - PPD, Power Substations

START Date: 
July, 2008

Current Role

  • Preparation and Monitoring of Master Programmes for various substation projects.
  • Cost loading and resource loading of the Construction Master Programme and monitoring the same.
  • Preparing Monthly Billing graphs for tracking, monitoring and controlling the cash flow of the project.
  • Tracking and control of the idle manpower and machinery cost incurred due to delay in the project.
  • Preparing weekly and monthly reports for tracking, monitoring and reporting the overall progress of the project to the Client.
  • Conducting p

Planning Engineer, Saipem, Kashagan Development Project

START Date: 
June, 2005
END Date: 
January, 2007

Kashagan Project (Agip/ENI) – Kashagan Vessel Assembly and Upgrade

Planning Engineer – Baku, Azerbaijan