PLANNING ENGINEER

PLANNING ENGINEER, Expert Systems Pvt Ltd, Lahore, Punjab Government Servants Housing Scheme

START Date: 
August, 2006
END Date: 
January, 2010

 

  1. Preparation of Master schedule using primavera p6 including resource & cost loading.
  2. Schedule update & progress monitoring.
  3. Generating weekly & monthly reports including ‘S’-curves for Client & management review.
  4. Generating progress report for site management review and analyzing current status of projects.
  5. Cost control by Optimization of Resources utilization.
  6. Preparation of Interim Payment Certificate
  7. Submittals for Project Execution (Bar Bending Schedule, Shop Drawings, etc)
Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
6000

Planning engineer, Chicago Maintenance and Construction Co LLC, GEMS Schools in Dubai

START Date: 
June, 2013

Planning and scheduling the project programme. Monitoring all the activites in detail and WBS level.

PLANNING ENGINEER, Overseas AST LLC co, Construction & EPC projects

START Date: 
June, 2008
END Date: 
August, 2009

1) Participate in bid and tender meetings, site visit and queries
2) Review of contracts, scope of work
3) Prepare execution plan, WBS and schedule of activity based on contract scope
4) Coordinate with estimating and operational group for budget and work schedule activity
5) Prepare cash flow based on estimated budget and integrate to schedule for resource loading
6) Monitor, track and update project status, and preparation of report for submittals
7) Perform schedule analysis for delays and impact to the existing schedule
8) Preparation of mitigation, recovery plan, a

Planning engineer, RDS, Various

START Date: 
January, 2010

Current Role is that I am a Planning Engineer on various projects

Planning Engineer, Sasol, Multi Projects

START Date: 
August, 2008

In Aug 2008, I moved to South Africa and stated working for Sasol Company. In the first year, I was in a Refinery and I did planning for small brown field projects. In refinery, Sasol was contractor. In second year, I took over some big projects and started working in Client side. A project in construction phase was the first project that I became involved. The main schedule was in Primavera 6. I checked the EPC contractor schedule as well as their progress.

PLANNING ENGINEER, El Seif Engineering Contracting Co. - Riyadh, Housing Residential Complexes (MOI). $1.4 Bln, in K.S.A

START Date: 
August, 2006

Planning,  Scheduling,  Progress  Tracking  Updating,  Monitoring,  Controlling  ,  Reporting  &    TIA    (Time Impact Analysis)

Experience Hours (Planning & Scheduling): 
27800
Experience Hours (Cost Management): 
1000

PLANNING ENGINEER, TFL, Streets Infrastructure - London

START Date: 
April, 2007

Planning Engineer with over 8 years experience in mining, aviation, construction and railways industries. I'm an expert in Primavera and experienced in the creation of resource and cost loaded programmes. I enjoy automating updates and reports using VBA and Primavera and I have experience with data migration and from SAP, MS Project and other databases to Primavera. I have been successful in the delivery of projects that meet client expectations, budgets and agreed specifications.

 

Planning Engineer, NSG Environmental Ltd, Nuclear Decommissioning

START Date: 
March, 2005
END Date: 
September, 2017

Planning Engineer working for a company that retrieves and encapsulates waste, working throughout the UK on various nuclear sites

Planning Engineer, EC Harris, Various

START Date: 
January, 2007
END Date: 
March, 2011
  • Responsible for assisting with overseeing the production and maintenance of construction programmes for numerous projects worth up to £50M
  • Facilitating smooth operations by adhering to the Critical Path method, calculating an effective sequence of activities, linking them together using all resources to best possible effect by anticipating demands, factoring in contingencies and alternative construction methods in case of changes in scope and monitoring progress through to timely and successful project completion
  • Extensive liaison with all stakeholders, forming clear li