Planning Engineer, Gulf Technical Construction company LLC, Multi Projects
Roles and Responsibilities:
· To produce Resource and Cost loaded Baseline and recovery programs for various projects in Dubai, Abu Dhabi and Saudi Arabia.
· To produce Tender programs for various projects in UAE, Saudi Arabia and Libya,
· To produce company’s cash in-flows and out-flows periodically,
· To produce resource histograms for different projects along with consolidated resource requirement.
· To produce procurement and shop drawings schedules for various projects in Dubai and Abu Dhabi,
· Monitoring three different projects,
· Lakeside Residence at IMPZ, Dubai from March 2010 – March 2011(3B+G+2P+23Flrs , 4 Residential Towers)
o Client :DAMAC
o Project Cost :370 Million
· Royal Amwaj resort and Spa, Dubai - April 2008 – Present ( 73 Villas, 2 Condominiums(B+G+8F), 3 lagoons )
o Client :Seven Tides
o Contract Cost :369 Million
· Mangrove Place, Abu Dhabi – October 2011 – Present (3B+G+2P+26 floors residential towers)
o Client :Luxury Real estate Developers
o Contract Cost :360 Million
· Schedule updates, progress monitoring and reporting,
· To track update information required for weekly and monthly reports to ensure it compliance with project completion date,
· To track and monitor shop drawings and material submissions,
· To review and evaluate subcontractor’s schedules, reports and other submissions to align as per schedule,
· Update procurement register and track material deliveries at site,
· To participate weekly progress and coordination meeting in order to discuss the status of the projects,
· Involved in preparing EOTs for different running projects.