I have some major concerns about revising the baseline. These concerns are generally relates to legal terms as our Contract clauses (not FIDIC or similar, tailor made) allows for Clients claims other than delay damages where the rate of progress is too slow than the planned. Contract also provides that; when the Contractor wishes to amend the approved programme, it shall be submitted again for approval. This gives a flexbility to amend a baseline.
Now the questions are the following;
1)What is common practice to revise the baseline? Would you update the schedule or just show nill progress and modify the durations, links etc and keep the data date same? The consequences of both options are the following;
a) where you are behind the progress and if the revised programme is approved with the updated information, you will literally recover your delay and the Client will not be able claim that you are behind the schedule anymore.
b) where you are ahead of the schedule you will just equalize your progress to planned which eventually loosing whatever you gained before. This gain will most probably be required during the remaining works.
2) During the course of the Works if you recognize that you have poor planning ie. the productivity parameters of the baseline is not realistic since you didnt have any realistic data within that enviroment while developing the L3 schedule and the resources has to be changed due to design development (for a design and built contract) would you revise your baseline accordingly or just keep the changes limited to updated schedule? If your answer is NO, how would you compare the actuals vs planned, as the activities has to be added/deleted due to design changes.
For your replies you should again note that these parameters specific for our contract;
1)this is a design and built contract where the changes in design due to design development does not constitute Variation.
2) only milestone within the time schedule is the completion date
thanks in advance
Replies