Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

A Case Study on The Implementation of Quality Function Deployment (QFD) in The Canal Reconstruction along Crude Oil Pipeline in

No replies
HERY MADA INDRA P...
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 6 Mar 2015
Posts: 7
Groups: None

Changing in scope during construction phase is the most common problems causing project delays among Indonesian contractors. Most of the scope changing is due to poor engagement with customer and to a failure in identifying customers’ needs during project scoping.

This paper aims to examine the aptness of QFD using HOQ in project planning and designing to guarantee that both the project requirements and project scope accommodate all the customer requirements, and to demonstrate the use of QFD during construction phases in a real project management implementation as control tools in the project construction.

The result of the QFD implementation using HOQ showed that 25 detailed final project scopes were developed from traditionally-generated nine project scopes.

It is concluded that the QFD is proven as a quality road map tools to help a project manager navigate the planning and construction process in project management. In addition, QFD is useful as smart sensitivity check when there are changes in the project requirements as all evolution in design is recorded from the beginning so that any alteration during the process of project planning is traceable.