Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Display Calender days

1 reply [Last post]
Luke Charet
User offline. Last seen 11 years 15 weeks ago. Offline
Joined: 25 Aug 2009
Posts: 18
Groups: None

Gday

 

A simple question which has already been answered in previous posts however i thought I might ask again. 

Can I display a calender days column. Activity #1 has 90 working days, which is how many calender days.......... Without using global change.

Thanks all, Merry Xmas

Replies

Raymund de Laza
User offline. Last seen 14 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762
Luke, Copy your original duration into a UDF then display it. Then change the default calendar with 7 days working days. Now you can see both working n calendar days. Hope this will help. Merry Christmas....