How to display No of Days in a month in TimeScale

2 replies [Last post]
Jagjit Singh
User offline. Last seen 8 years 42 weeks ago. Offline
Joined: 18 Jun 2016
Posts: 7
Groups: None

Hi

 

   How to display No of Days in a month in TimeScale considering 30 days as 1 month . I want to display like this in TimeScale and draw Gantt Chart accordingly

30        60          90         120        150        180  & so on till 450

 

Thanks

Replies

Zoltan Palffy
User offline. Last seen 23 weeks 4 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

view timescale 

then at the bottom 

ordinal dates 

then ordinal date interval is days

Jagjit Singh
User offline. Last seen 8 years 42 weeks ago. Offline
Joined: 18 Jun 2016
Posts: 7
Groups: None

Hi

 

  Currently it is displayed as  Jun 2016 , August 2016 , Septemeber 2016 and so on