Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to create a WBS UDF that can be displayed at Activity level, same as WBS Category can be displayed.

No replies
Rodney Jones
User offline. Last seen 41 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Hello Everyone,

 

I am wondering how to create a WBS UDF that can be displayed at Activity level, same as WBS Category can be displayed and grouped at Activity Layouts as a column.

Or a WBS code that can be displayed and grouped by at Activity level.

 

Thanks,

 

Rod

Rodney Jones
User offline. Last seen 41 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Closed.

 

Rodel, Yes, I ended up adding an Activity code. Thanks, Rod

Rodel Marasigan
User offline. Last seen 13 weeks 2 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Rodney,

WBS UDF is only available to assigned on WBS table, if you wanted to Activity Level you can define WBS at Activity UDF. There is no WBS Code or you mean Project Code? Again, Activity Code can be define a WBS definition with hierarchy on single activity code type at activity level. You can create a new WBS definition with hierarchy as up to 20 levels or depending on maximum tree level setting you assigned on Admin preferences.