Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Why the baseline project start change when I do F9

4 replies [Last post]
walid Lahiani
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Good morning,

Normaly ,baseline dates don't change when we update!?

Thanks

Replies

walid Lahiani
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Good morning,

I did right click,bars,i checked primary baseline,so I had the bar target graphic

thanks,

Forrest Chen
User offline. Last seen 8 years 19 weeks ago. Offline
Joined: 29 Dec 2011
Posts: 10
Groups: None

right click on gant chart ----- choose 'Bars' ---- find the column named 'timescale' ----- change whatever is chosen into 'project baseline' (same row as project baseline)

cheers

walid Lahiani
User offline. Last seen 8 years 17 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Yes,

In Project->Assign baseline->My choice was current project and now I changed it to Target which I did with Project->maintain baseline

 

Thank you

Raymund de Laza
User offline. Last seen 3 days 6 hours ago. Offline
Joined: 22 Nov 2009
Posts: 762

Walid,

You might have assigned the current project as your baseline.

Please investigate.....