Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Why when changing a resource does it change the 'Budgeted at completion' to equal the duration?

2 replies [Last post]
DAVID SMITH
User offline. Last seen 11 years 20 weeks ago. Offline
Joined: 24 Mar 2004
Posts: 28

When I manually change a resource, it changes the budgeted units to equal the duration on the activity.

what setting is doing this, i presume it is a tick box somewhere.

Can anyone please help?

Many thanks

Dave

Replies

Alfredo Jr. Hubilla
User offline. Last seen 5 years 23 weeks ago. Offline
Joined: 6 Feb 2012
Posts: 20

Try go to the Projects Details, Resources tab, and tick the Resources can edit activity assignment percent complete..

 

Hope this can help.

Raymund de Laza
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Dave,

Make the Max Units/Time of the resource the same as the previous. 

Hope this will help.