Restore Base line

2 replies [Last post]
Arun Vasanth
User offline. Last seen 5 years 19 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Dear friends Please guide me how to restore the base line program from the updated program. I made a big mistake .I prepared the base program and updated with base prgram as current project .I did nt mmake a single copy or back up of the base program & the progress updation is almost 40 % completed. Regards Arun .V

Replies

Arun Vasanth
User offline. Last seen 5 years 19 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar

 

Thank you Jashhhh

Jash Sales
User offline. Last seen 12 years 25 weeks ago. Offline
Joined: 8 Dec 2009
Posts: 27
Groups: None

Arun,

Go to Project ~ assign baseline: used <current project> as your project baseline/ user primary baseline, then go to maintain baseline~ click restore.

gudluck!