Updating the assigned base line

3 replies [Last post]
Sanjay Rao
User offline. Last seen 5 years 17 weeks ago. Offline
Joined: 17 Jun 2008
Posts: 22
Groups: GPC Qatar
Hi every one
During updating the assigned base line ( maintaining baseline ) to a project do we need to update the activity/ milestone assigned in revised program.

Replies

Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Sanjay,

There are two ways on how to update your Baseline.

1. Restore your Baseline Schedule and update it in accordance to your new data date and % complete, and whatever you need to update.

2. You can update without restoring but this is more complicated than #1.

It depends on what you want to update in the "Update Baseline Options".

Regards,

Arnold
Sanjay Rao
User offline. Last seen 5 years 17 weeks ago. Offline
Joined: 17 Jun 2008
Posts: 22
Groups: GPC Qatar
i want to update Base line
Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Sanjay,

Which one do you want to update, Baseline or Revised Programme?

Regards.