Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Updating the assigned base line

3 replies [Last post]
Sanjay Rao
User offline. Last seen 4 years 51 weeks ago. Offline
Joined: 17 Jun 2008
Posts: 22
Groups: GPC Qatar
Hi every one
During updating the assigned base line ( maintaining baseline ) to a project do we need to update the activity/ milestone assigned in revised program.

Replies

Arnold Puy
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Sanjay,

There are two ways on how to update your Baseline.

1. Restore your Baseline Schedule and update it in accordance to your new data date and % complete, and whatever you need to update.

2. You can update without restoring but this is more complicated than #1.

It depends on what you want to update in the "Update Baseline Options".

Regards,

Arnold
Sanjay Rao
User offline. Last seen 4 years 51 weeks ago. Offline
Joined: 17 Jun 2008
Posts: 22
Groups: GPC Qatar
i want to update Base line
Arnold Puy
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Sanjay,

Which one do you want to update, Baseline or Revised Programme?

Regards.