Summarization % of Base Line for P5

3 replies [Last post]
Omar Abdull Sattar
User offline. Last seen 11 years 43 weeks ago. Offline
Joined: 17 Dec 2006
Posts: 5
Groups: None
for P5 I can not see the Summary% for the Baseline when I am trying to make comparison with the actual. By the way I can see BL Original Duration , BL Start & BL Finish Date in the Summary Band and also I can see all BL percentages for all activities except the summary band is coming Empty for WBS or Activity Code Summary.

Replies

Karim Mounir
User offline. Last seen 10 years 7 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi Omar,
Checkout this post:
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=30849
it may helps.

Regards,
Karim
Omar A.S.
User offline. Last seen 17 years 25 weeks ago. Offline
Joined: 11 Apr 2007
Posts: 3
Groups: None
Dear IC Quiamco

Yes I mean Unit% & Duration % and another things BL Remaining Duration in Summary

Thanks

Omar A.S
IC Quiamco
User offline. Last seen 13 years 32 weeks ago. Offline
Joined: 20 Dec 2002
Posts: 48
Check what percentage column are you using. In the list of available % column two does not have summary (Activity & Physical % Complete).

Commonly use Duration % column.