Global Change for Calendars

2 replies [Last post]
Jeremey Smith
User offline. Last seen 13 years 39 weeks ago. Offline
Joined: 16 Jun 2011
Posts: 15
Groups: None

What criteria need to set up in Global Change to change the Calendar from 7 weeks to 5 weeks which may change calendar of all actvities?

Thanks

Replies

Ranjit Kumar Kumar
User offline. Last seen 2 years 22 weeks ago. Offline
Joined: 17 Sep 2009
Posts: 6
Groups: None

Hi Jeremy Simth,

Select Enterprise > Calendar > Add > Select any Calendar from the existing calendar > Modify > Work week > Which day you want to off put 0 or other wise put all 8 hours then it will change from 5 work days to 7 work days > Click on the Default.

 

Assigning the 7 days work week to all the activities.

View > Columns > Click on the General and find out the Calendar > Ok

 

Change the existing calendar by the new calendar in one cell.

After wards click on the new cell (new calendar cell) then use the command shift and select all the activities > go to the Edit > fill cell.

I hope it will work

Thanks and regards,

Ranjit

Shah. HB
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi Jeremy Smith

1. Create a calendar of 5 Weeks 

2.Filter the activities you need change (If any )

3.Use file down option to replace 7 weeks to 5 weeks

///Is it weeks or days?///

Regards

Shahul