Hi all,
Apologies if this has been posted - I did try and look for a similar example. I'm trying to understand why my durations are changing when I change from a normal 5d week calendar (8hrs per day) to a 5d week calendar with non-working days throughout (<5d week calendar).
No changes of hours for each day or changes to the activities themselves. To try and illustrate the issue;
1. Activity A - 5d - on a normal calendar (commencing Monday and completing Friday)
2. Change calendar of Activity A to 5d calendar with blockout days (non-working days)
3. Result; Activity A still ends on the Friday, but duration has been reduced from 5d to 4d, while the expectation is that the duration would remain the same and Activity A would end on the following Monday
Hope that makes sense, and appreciate any assistance / explanation
Edit; I should add that there're no expected finish dates or constraints, etc.
Replies