Global change resource dates

1 reply [Last post]
Anthony Peters
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 5 Apr 2007
Posts: 18
Groups: None

Is there any global change parameters that will align resource start/finish to activity start finish. I have about 300 activities that need alligning and need a quick way to do it. When i tried a global change, it would only affect activities OR activity resource assignments, not a mixture?

Replies

Raymund de Laza
User offline. Last seen 1 week 17 hours ago. Offline
Joined: 22 Nov 2009
Posts: 762

> make sure that calendar used for the resources is matching with activity calendar.

> make sure that effective date of Resource units and prices is before the start date of the project.

>make sure that resource curve used will distribute resources from the beginning through the end of the duration of the activity.

> Scheudle the project to make sure changes effects.

>Refresh by keying F5.

 

Hope this will help.