Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Global Change - Status Indicator for expiry date alerts

3 replies [Last post]
THEO MANIFAVAS
User offline. Last seen 5 years 3 weeks ago. Offline
Joined: 11 May 2020
Posts: 3
Groups: None

hi

wandering if someone can please help me with this

i have created a User Defined Field (UDF) named Insurance Expiry which i have allocated this with a date field so i can track when a resources liabilty insurance expires. 

i have also created a UDF called Insurance Indicator which i have assigned Indicators as the date type for this UDF

 

i then created 3 global changes

7401
global_change.jpg

 

which i want to work as follows

INSURACE EXPIRED = red cross indicator when Insurance Expiry date is after the data date (DD)
INSURANCE EXPIRY WARNING = yellow warning indicator when Insurance Expiry date is within 10 days after the DD
INSURANCE OK = green tick indicator when Insurance Expiry date is 10 days plus after the DD

So the idea is that we enter the Insurance Expiry date for each resource and then based on scheduled DD, the Insurance Indicator column will display the correct indicator based on the parameters as detailed above. 

I can't get this to work however so not sure if i'm entering the info wrong in the global change? see below

7402
modify_global_change.jpg

or is there something else i'm meant to be doing to get it to work?
 

thanks in advance

 

Replies

Zoltan Palffy
User offline. Last seen 1 week 35 min ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

when you say i have created a User Defined Field (UDF) named Insurance Expiry which i have allocated this with a date field so i can track when a resources liabilty insurance expires. 

did you use start or finish date ?

THEO MANIFAVAS
User offline. Last seen 5 years 3 weeks ago. Offline
Joined: 11 May 2020
Posts: 3
Groups: None

hi

thanks for pointing that out

yes i did realise the last Global Change had CD instead of DD
I was just trying to see if this worked over DD as i could't get the global change to work at all in terms of displaying the indicators within the activities view (the global change processes once you click Apply Change in terms of providing the report however this doesn;t then filter through into the activities view in the column) i.e this section remains blank 

 

7403
capture23.jpg

 

just wandering if i'm missing a step or doing something wrong in the filter which is stopping it from displaying correcty?>(noting that the DD i have using the above exammple is set to 17/5/20 so the INSURANCE EXPIRY WARNING INDICATOR should come on but it doens't for some reason)

Zoltan Palffy
User offline. Last seen 1 week 35 min ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

the last one you have cd not DD in the value