Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Confusion between budget....

1 reply [Last post]
Irfan Khan
User offline. Last seen 28 weeks 3 days ago. Offline
Joined: 19 Jul 2009
Posts: 138
Hi to all,

Can anybody tell me that what is the difference between Budget At Completion > At Completion Total Cost & Original Budget.



Thanks,,,


Replies

Rodel Marasigan
User offline. Last seen 1 week 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Irfan,
Original Budget is Contract Amount including Overhead, Provisional Sum, Profit, Margin etc...

Budget At Completion (BAC) = Budget + Approved Variation/Changes use as base to measure Earned Value.
AT Completion = Actual cost + Remaining cost = Forecast At Completion