Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Duration Type / Percent Complete - Absolute Confusion

1 reply [Last post]
Matthew Lovkis
User offline. Last seen 17 years 4 days ago. Offline
Joined: 26 Nov 2006
Posts: 19
Groups: None
Hi There,

I am struggling to come to terms with the duration type and percent complete functions of P3e. I have read numerous texts and everything I can find on the subject.

All I want is to be able to update an activity where the At Complete Duration doesn’t change when I update the Actual Units.

However when I have an activity that is Fixed Duration and Units, and the percent complete type is Units... when I update the units and the data date... it increases the At Complete Duration. How can I possibly keep the at complete duration the same throughout?

Thanks,

Matt Lovkis

Replies

Laurence Potgieter
User offline. Last seen 13 years 44 weeks ago. Offline
Joined: 7 Dec 2006
Posts: 6
Groups: None
you are not the only confused one, don’t worry. The number of permutations that can be implemented with all the activity progress types, resource progress methods, percent completes, etc. etc. are many.
However, try Enterprise - Projects - select project - Calculations tab - there you see some radio button options about this.
It’s all very complicated, no-one argues about that fact, not even the agents.