Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Confusion between “% Complete Type” ?

1 reply [Last post]
Irfan Khan
User offline. Last seen 28 weeks 22 hours ago. Offline
Joined: 19 Jul 2009
Posts: 138

hi to all friends,

 

I have a cost loaded schedule and before my “% Complete Type” was fixed on “Duration” and my “Performance % Complete” Progressed up to 39.10% but when I changed my “% Complete Type” from “Duration to Physical” than my “Performance % Complete” showing 28.07%.
 
Can anybody explain me why this happening?

Thanks in advance……..



Mohd. Irfan Khan

Replies

Shah. HB
User offline. Last seen 50 weeks 4 hours ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi Irfan check the below matrix

Percent Complete Type

The activity percent complete type is one of "Duration", "Units", or "Physical". The percent complete type controls whether the Activity % Complete is tied to the Duration % Complete, the Units % Complete, or the Physical % Complete for the activity. Set the percent complete type to "Duration" for activities which are duration driven, for example, administration tasks and training classes. Set the percent complete type to "Physical" for activities which are work-product driven, for example, creating a document or a product. Set the percent complete type to "Units" for activities which are work effort driven, for example, providing a consulting service.

Activity Percent Complete Fields

Physical % Complete

The activity physical percent complete. The physical percent complete reflects the actual progress made on the activity's work products so far. Physical percent complete can be manually entered by people familiar with the status of the activity's work products or it can be based on the completion of assigned Steps. Always in the range 0 to 100.

Duration % Complete

The percent complete of the activity duration. Computed as ((Planned Duration - Remain Duration) / Planned Duration) * 100. Always in the range 0 to 100. The planned duration is taken from the current plan, not from the current baseline.

Duration % of Planned

The activity actual duration percent of planned. Computed as (Actual Duration / BL Duration) * 100. The value can exceed 100. The BL Duration is the activity's at complete duration from the current baseline.

Activity % Complete

The activity percent complete. This value is tied to the activity Duration % Complete, Units % Complete, or Physical % Complete, depending on the setting for the activity's Percent Complete Type, which is one of "Duration", "Units", or "Physical". Always in the range 0 to 100.

Schedule % Complete

The Schedule % Complete specifies how much of the activity's baseline duration has been completed so far. Computed based on where the current data date falls between the activity's baseline start and finish dates. If the data date is earlier than the BL Start, the Schedule % Complete is 0. If the data date is later than the BL Finish, the Schedule % Complete is 100. The Schedule % Complete indicates how much of the activity duration should be currently completed, relative to the selected baseline.
Note: Summary Schedule percent complete when displayed on an organize band, will ALWAYS be calculated as (BCWS* 100) / BAC, regardless of what earned value technique is selected for the activity's WBS.

Performance % Complete

Performance percent complete is used to compute earned value and may be based on the Activity % Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far.
Note: Summary Performance percent complete when displayed on an organize band, will ALWAYS be calculated as (BCWP * 100) / BAC, regardless of what earned value technique is selected for the activity's WBS.

 

Cost Related Percent Complete Fields

Labor Cost % Complete

The percent complete of costs for all labor resources assigned to the activity. Computed as (Actual Labor Cost / At Complete Labor Cost) * 100. Always in the range 0 to 100.

Non-Labor Cost % Complete

The percent complete of costs for all non-labor resources assigned to the activity. Computed as (Actual Non-Labor Cost / At Complete Non-Labor Cost) * 100. Always in the range 0 to 100.

Expense Cost % Complete

The percent complete of costs for all expenses associated with the activity. Computed as (Actual Expense Cost / At Complete Expense Cost) * 100. Always in the range 0 to 100.

Cost % Complete

The percent complete of costs for all labor resources, non-labor resources, and expenses for the activity. Computed as (Actual Total Cost / At Complete Total Cost) * 100. Always in the range 0 to 100.

Cost % of Planned

The activity actual cost percent of planned. Computed as (Actual Total Cost / BL Total Cost) * 100, or equivalently as (ACWP / BAC) * 100. The value can exceed 100. The baseline total cost is the activity's at complete cost from the current baseline.


Unit Related Percent Complete Fields

Units % Complete

The percent complete of units for all labor and non-labor resources assigned to the activity. Computed as (Actual Units / At Complete Units) * 100. Always in the range 0 to 100.

Labor Units % Complete

The percent complete of units for all labor resources for the activity. Computed as (Actual Labor Units / At Complete Labor Units) * 100. Always in the range 0 to 100.

Non-Labor Units % Complete

The percent complete of units for all non-labor resources for the activity. Computed as (Actual Non-Labor Units / At Complete Non-Labor Units) * 100. Always in the range 0 to 100.


WBS Level Percent Complete Field

Steps % Complete

The percent complete using the WBS Milestones that are assigned to a WBS level. Computed as Actual Weight of Completed Milestones / Total Possible Weight of All Milestones

Regards

Shahul