Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Why does Progress % does not apper while summarizing

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 6 years 40 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Why does, while we are summarizing the project with wbs level , any progress % (for eg activity % complete column), does not show any % at WBS level , even when we add resource & cost for all activities.

The summarized % column is blank....

Can anyone explain......

Replies

Rodel Marasigan
User offline. Last seen 1 week 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Haresh,
There are only two fields that would not summarize total in summary band, Physical % complete and Activity % Complete which is represented by Performance % Complete.
There are 3 types of % complete type, Duration, Unit and Physical. Duration is base on duration (Yr, Mth, Wk, Day or Hr), Units is labor, non-labor and material and Physical = Physical.
All three of them are represented by Activity % complete and Performance % complete (which ever is set on % complete type) therefore if total is required in summary band Performance % Complete should be used and if not then Activity % Complete is the appropriate to use.

To show the total in Summary Band, under Group & Sort -> Display Option tick Show Group Total.