Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Why does P6 does not show BL2 % Complete

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 6 years 23 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219

Dear All,

I have assigned two programs as primary baseline and secondary baseline. But i am not able to get the column showing % complete for the secondary baseline program i.e. BL2.

How to solve this problem.

 

Pls do reply.

 

regards,

 

Haresh Jayanth

Replies

michael ramos
User offline. Last seen 7 years 21 weeks ago. Offline
Joined: 10 Feb 2009
Posts: 25
Groups: None

you can try a workaround

assign your BL2 as project baseline and copy the schedule % to UDF using global change (after shifting the data date)

then assign BL1 as project baseline and put your BL2 as primary

now you can compare sched % (BL1) and UDF (BL2)