All,
I’m not sure if this topic had been discussed in this forum. Anyway, I need help.
The variance values between the baseline program and the current updated program seems odd to me. The current program is behind the baseline program however, when I displayed the Variance – BL Project Finish column, the activity which is behind the baseline shows a positive variance. Whereas, when I looked at the rolled up value in the WBS level, the variance is showing a negative value which is correct I supposed. Here are the details:
WBS Level / Activity Level
BL Project Start: 26Jun08 / 26Jun08
BL Project Finish: 24Aug08 / 01Jul08
Start (Current): 08Sep08A / 08Sep08A
Finish (Current): 06Jan09A / 11Oct08A
Variance BL Project
Finish: -109 days / 84 days
Obviously, my question is why the variance in the activity shows positive instead of negative? Did I miss any of the setup?
Regards,
Louie